AWPR PROJECT
Date: Tue 28th November 2017These are the pictures of bifurcation in situ shuttering work on the fast link of the AWPR project.
A base was poured first, which was finished with a texture roller for the main pour to bind to, the shutters were then stood and fixed once the base had cured. We then poured concrete into the shutter and gave it a steel float finish. These will be struck the next day and any air holes left will be sealed with a bag wash mixture that matches the colour of the wall.
Back to News